ATP Post Plan Processing - Performance Problem

(Doc ID 1378485.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Global Order Promising - Version 12.1.3 and later
Information in this document applies to any platform.
*** Checked for relevance on 31-DEC-2014 ***

Symptoms

On : 12.1.3 version, Data Collections
ATP (Available To Promise) Post plan processing takes more than 5 hrs to complete.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Login with Advanced planner responsibility.
2. Navigate to View - Requests - Submit a requests
3. launch the ATP plan

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms