Order Modifiers Ignored For Hard Pegged Items - Project Environment (Doc ID 1384480.1)

Last updated on APRIL 07, 2023

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Customer on Project Manufacturing Planning
Reservation level = Planning group
Hard pegging level = Project-Task
Lot for lot = cleared (not ticked)

Order modifiers ignored for hard pegged items

The issue can be reproduced at will with the following steps:
1.A hard pegged item is set up with a Fixed Lot Multiplier in Organization item window in a project manufacturing  organization
2.A forecast is created for same item with project and task
3. A project ASCP plan is run for this item that should recommend a planned order.
4. ASCP does suggest a planned order but the planned order quantity does not respect the fixed lot multiplier

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.