How to Restart Project Scheduled Services in P6 That Are Stuck in a Running or Delegated Status
(Doc ID 1418876.1)
Last updated on DECEMBER 13, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 8.1 2.0 and laterInformation in this document applies to any platform.
Goal
When the P6 EPPM managed server/P6 Services process or the server itself is restarted, a job in Running (or Delegated) status remains in its previous state and is effectively a "hung" job. The job can be cleaned up and set to restart on startup by making a configuration change.
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |