Activity Dates Not Updated After Executing API Code To Update Activity Status And Dates (Doc ID 1423453.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version: 6.2 and later   [Release: 6.2 and later ]
Information in this document applies to any platform.

Symptoms

When executing API code that updates the Status and Dates of an activity the Status updates correctly but Dates are not updated. Updating the activity Status from COMPLETED to NOT_STARTED and updating the Planned Start and Planned Finish Dates the Status updates successfully but the Planned Dates failed to update.

Cause

Sign In with your My Oracle Support account