Values Remain in Materials Presently Stored (Column F) Column in Generated Requisition

(Doc ID 1441379.1)

Last updated on JANUARY 12, 2017

Applies to:

Primavera Contract Management - Version 10.0 and later
Information in this document applies to any platform.

Symptoms

After generating the next Requisition in an existing Requisition series, the line item values from the Materials Presently Stored (Column F) column in the previous Requisition are still in the Materials Presently Stored (Column F) column in the new Requisition.

Cause