Goal

We have set the following plan option in our MRP.
Schedule By = "Request Arrival Date".
We expect that with this option the planned orders should be generated with Sugg Due Date = Sales Order Line Request Date.

But still the planned orders are generated with due date = Sales Order line Scheduled Ship Date.
 