Overlay Patch Cannot Fully Sync Valid_to Pipeline After Cancel Product (Doc ID 1455179.1)

Last updated on AUGUST 28, 2012

Applies to:

Oracle Communications Billing and Revenue Management - Version 7.3.1.0.1 to 7.3.1.0.1 [Release 7.3.1]
Information in this document applies to any platform.

Symptoms

Our issue is the following:

When we cancel a product from infranet, the resource validity shows wrong values in pipeline memory. However, the validity does get updated to the correct values after restart of the pipeline.


Steps to reproduce:

1. Start Batch pipeline
2. Perform the test case
  a. 31 Dec 2011 03:00, Create account as DOM 10
  b. 1 Jan 2012 22:00, Purchase product with effective date as 1/1/2012 20:00:01
  c. Run pin_bill_day
  d. 6 Jan 2012 22:00, Cancel the product pruchased in step 2
3.Take the pipeline memory dump.
4.Restart Batch pipeline
5.Take the pipeline memory dump.
6.Compare the output from 3 and 5.

From the balance dumps the validity of the non-currency resource before and after pipeline restart (ie after the cancellation of the product) we could see the validity of the resource as follows:
 
  Before pipeline restart:
  Valid_to :  2012/01/06 14:00:00
 
  After pipeline restart:
  Valid_to : 2012/01/09 16:00:00 

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms