Missing Recurring Events After Migration To Calendar Server 7

(Doc ID 1459548.1)

Last updated on AUGUST 03, 2015

Applies to:

Oracle Communications Calendar Server - Version 6.3 to 7.1 [Release 6.3 to 7.0]
Information in this document applies to any platform.

Symptoms

Migrating from Calendar 6.3 to Calendar Server 7u2 (CS7)

If there are two recurring events with the same UID in the Calendar 6 environment, one of them fails to migrate to Calendar 7 without giving any error.

We have done a comparison on resource calendar events (in this example called "MeetingRoom1") after migrating to CS7 and found that a recurring meeting, (Meeting Summary: "SPIN Weekly meeting"), is missing after the migration.  There is no error reported in either the master_log or in the calendar_log about this.

The resource calendar in question is 'MeetingRoom1'.  The two events that have the same UID are:

000000000000000000000000000000004ef4c777000010c700000a120000302a SPIN Weekly meeting - Netapp Design Review
000000000000000000000000000000004ef4c777000010c700000a120000302a Unity-to-Unity Connection "pre-project" Planning


Event 2 "Unity …" has migrated and Event "SPIN…" is missing in CS7.

An output of csexport did not include the "SPIN Weekly meeting".  An output of cscomponents -v does.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms