Planned Orders For Safety Stock Needed In Future Are Generated With Today As Suggested Due Date

(Doc ID 1465674.1)

Last updated on SEPTEMBER 09, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 11.5.10.2 to 12.1.3.7 [Release 11.5 to 12.1]
Information in this document applies to any platform.

Symptoms

12.1.3 version, Memory Based Planner, Source instance version 11.5.10.2


In constrained EDD plan the planning generates planned orders to replenish to safety stock level. Although the replenishment is needed in the far future (beyond the lead time of the item) still all planned safety stock orders have a suggested due date of today.



STEPS:
1.Run Data Collections
2.Run the plan

Cause