Summarization Project Scheduled Service Job Takes A Long Time To Complete Against A Group Of Projects Which Have Already Been Summarized (Doc ID 1482530.1)

Last updated on AUGUST 31, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.2 and later
Information in this document applies to any platform.

Symptoms

When running a summzaration scheduled services job in P6 EPPM r8.2:

ACTUAL BEHAVIOR
----------------------
Each time a summarization project scheduled service job runs, it takes a large amount of time or does not complete at all, when the job is setup to run against all the projects in the database, or a large grouping of projects.  

Note:  Even if the summarization job has just run and completed, a second execution of the job results in the same issue (large amount of time to complete or fails to complete at all), even when there are no changes made to any of the projects for the summarization job to complete.  

EXPECTED BEHAVIOR
----------------------
A summaration job run against a group of projects which have already been summarized should complete in a much shorter timespan then the first execution of a summarization job.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References

My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.