Primary Resource Can Mark Activities As Completed In Progress Reporter When The Option In Project Preferences Is Not Checked

(Doc ID 1493888.1)

Last updated on DECEMBER 05, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.1.1.0 to 15.2.0.0 [Release 8.1 to 15.2]
Information in this document applies to any platform.

Goal

This document explains why the Primary Resource can check the Finish of an Activity in Progress Reporter when the Project Preference for 'Primary resources can mark activities as completed' is NOT checked.