Level Of Effort Activity Does Not Get Actual Start From Predecessor Activity (Doc ID 1498838.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Information in this document applies to any platform.

Symptoms

A Level of Effort activity has both Predecessor and Successor activities in a different project.  When the Project containing the Level of Effort activity is scheduled, the duration of the LOE matches the duration of the Predecessor and Successor activities in the other project.  However, the Actual Start does not translate from the other project to the LOE activity.

Cause