BRM 7.4 PCM_OP_AR_EVENT_ADJUSTMENT Failure With Multiple Events For Adjustment and One of the Events In the List Has No Balance Impact

(Doc ID 1504643.1)

Last updated on NOVEMBER 30, 2012

Applies to:

Oracle Communications Billing and Revenue Management - Version to [Release 7.4.0]
Information in this document applies to any platform.


The PCM_OP_AR_EVENT_ADJUSTMENT opcode accepts multiple events for adjustment, however, when any of the events in the list has NO balance impact, the opcode exits with ERR_BUF set, without adjusting the other events.
The error indicates it failed in getting the ITEM_OBJ from optional BAL_IMPACTS of the event.

    <field num=PIN_FLD_ITEM_OBJ:7,107 recid=0 reserved=0 reserved2=0 time(sec:usec)=0:0>
    <facility=0 msg_id=0 version=0>