Cannot Give Activity An Actual Finish (Doc ID 1507216.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Information in this document applies to any platform.

Symptoms

 When trying to place a check in the Finished box, on the Status tab of the Activity Details view, the checkmark will immediately remove itself from the box and an Actual Finish cannot be placed on the activity.

Cause