Durations in a Calculated Value Column Display in Hours Regardless of Duration Format set in Plan Options. (Doc ID 1509200.1)

Last updated on JULY 28, 2017

Applies to:

Primavera Risk Analysis - Version 8.7.0052 and later
Information in this document applies to any platform.

Symptoms

When using a Calculated Value Column to calculate a duration, the result will be displayed in Hours if extra arithmetic is used in the formula. This will occur regardless of Planning Units used for Plan and Duration Format setting in Plan Options.

For example, when using the formula "PF - PS + 1" to calculate the duration between Task Start Date and Finish Date, the value is given in hours.

Note: The + 1 is used in the Formula because duration calculated using "PF - PS" will be an hour less than expected. This is by design and documented in Bug 14834591.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms