Symptoms

Open past due firm purchase order which are pegged to sales orders. ATP plan is not honoring the post processing lead time of the item while calculating the suggested ship date of the sales orders.
Suggested ship date should be equal to suggested dock date + post processing lead time. Its working fine for any future firm PO but not for any past due PO.

Cause