Users Cannot Add Activities To Timesheets in Progress Reporter When Running On WebSphere Application Server (Doc ID 1543422.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Professional Project Management - Version 7.0 SP2 and later
Primavera P6 Enterprise Project Portfolio Management - Version 7.0 SP2 and later
Information in this document applies to any platform.

Symptoms

On :  7.0 SP2 version, Primavera P6 Professional Project Management,TimeSheet Module, WebSphere Application Server

ACTUAL BEHAVIOR  
---------------
When users try to add activities, they are unable to see them on their Time Sheets. When the users pull up Progress Reporter, their time sheet will be blank.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1.Log into Progress Reporter

2. Go to Action > Add activity

3. Go to PR > Timesheet

No errors related to this issue are saved in the Progress Reporter log files. (Any log level)

Cause

Sign In with your My Oracle Support account