MSCSCPSOLVE Validation Error - AllOf Resources - Lot Multiple, Duration

(Doc ID 1545498.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Information in this document applies to any platform.
**Checked for relevance on 07-Jan-2015**

Symptoms

When attempting to solve a PS Plan the following error occurs.

ERROR
-----------------------

MSCSCPSOLVE module: Solve On Server

Message Type: Error
Time: 02/19/13 11:46:52
Message: Validation Error - AllOf Resources - Lot Multiple, Duration (Resource Set): Some of the members in AllOf Resources - Lot Multiple, Duration do not have a lot-multiple specified: 3:178055:275:178165:275:178181:275:178311:275:178487:275:1047:1, 2:178055:275:178165:275:178181:275:178287:275:747:1:178311:275, 4:178055:275:178165:275:178181:275:178291:275:751:1:178311:275, 1:178055:275:178165:275:178181:275:178311:275:178489:275:1049:1, 0:178055:275:178165:275:178181:275:178289:275:749:1:178311:275

It appears to be the case that this occurs where the resource is set up as Schedule to Instance and there is an alternate resource. As a consequence the AllOf Resources that are snapshot has the primary resource (and alternate to primary) removed and hence this appears to be a snap shot issue rather than an engine issue




Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms