How to enable "Allow users to enter negative hours" feature? (Doc ID 1548167.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Professional Project Management - Version 8.2 SP1 and later
Information in this document applies to any platform.

Goal

Why does "Apply Actuals" not update the activity with a negative value from the Timesheet?

For example, If user entered '-50' units in Timesheets and then runs 'Apply Actuals', the value in P6 is '0', NOT '-50'.

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms