BL Project budgeted units do not change after updating baseline.

(Doc ID 1559429.1)

Last updated on MARCH 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Information in this document applies to any platform.


On : 7.0 SP5 version and later, P6 Project Management Client

After removing resource on activity, resetting the budgeted units to zero, and updating the baseline, the BL project labor units are not zeroed out.

When resource is removed, budgeted units are set to zero, and Update Baseline is run, the BL project budgeted units should be zeroed out.

The issue has the following business impact:
Due to this issue, users cannot display the proper BL project budgeted units.