EDD Plan Shows Changeover Duration = 0 For Sequence Dependent Setup (SDS) in ASCP Plan Output (Doc ID 1572403.1)

Last updated on NOVEMBER 16, 2016

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

Plan is NOT optimized - Decision rules enabled Use End Item Substitution and Use Alternate BOM/Routing.  Constrained planning

Running EDD Classic Constrained plan 91 days/4 weeks/5 periods with 10 days minutes/10 days hours/71 days days - plan is NOT optimized - Decision rules enabled Use End Item Substitution and Use Alternate BOM/Routing

Collection Workbench shows correct Changeover Duration that users setup in source Instance BOM / Routing / Resources - query resource - select Setups button - Select the appropriate setup - select Changeovers button - setup the duration for the different setup/changeovers. Run collections and the data shows as expected in View Collected Data.  However ASCP Workbench is NOT CORRECT after running the plan. Changeover Duration = 0 for all resources.


 

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms