Planned Orders Not Generated By ASCP Plan

(Doc ID 1572475.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.1 and later
Information in this document applies to any platform.

Symptoms

 

After running ASCP Plan, Users there is demand for the item and there is no on hand.
The ASCP Plan did not generate a planned order for the item. The planning time fence days is 0
and planning time fence date is NULL.

 

EXPECTED BEHAVIOR
-----------------------
Expect planned orders for supply to be generated properly to meet demand


STEPS
-----------------------
The issue can be reproduced at will with the following steps:

1. Advanced Supply Chain Planner Responsibility
2. Launch ASCP Plan
3. Review workbench data



Cause