Changing Original/Planned Duration, or Budgeted/Planned Units or Cost Does Not Update Remaining Duration, or Remaining Units or Cost

(Doc ID 1573019.1)

Last updated on NOVEMBER 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Primavera P6 Professional Project Management - Version 7.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Primavera P6 Standard Project and Portfolio Management Cloud Service - Version 17.7 and later
Information in this document applies to any platform.

Symptoms

On Not Started activities, when modifying the value for the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost, the corresponding value of the Remaining Duration, Remaining Units, or Remaining Cost is not changing. The reverse is also true: when modifying the Remaining Duration or Remaining Units, the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost are not updating.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms