Changing Original/Planned Duration, or Budgeted/Planned Units or Cost Does Not Update Remaining Duration, or Remaining Units or Cost
(Doc ID 1573019.1)
Last updated on APRIL 28, 2023
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and laterPrimavera P6 Standard Project and Portfolio Management Cloud Service - Version 17.7 and later
Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Primavera P6 Professional Project Management - Version 7.0 and later
Information in this document applies to any platform.
Symptoms
On Not Started activities, when modifying the value for the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost, the corresponding value of the Remaining Duration, Remaining Units, or Remaining Cost is not changing. The reverse is also true: when modifying the Remaining Duration or Remaining Units, the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost are not updating.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |