Changing Original/Planned Duration, Or Budgeted/Planned Units Or Cost Does Not Update Remaining Duration, Or Remaining Units Or Cost (Doc ID 1573019.1)

Last updated on JUNE 08, 2016

Applies to:

Primavera P6 Professional Project Management - Version 7.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Information in this document applies to any platform.
***Checked for relevance on 08-Jan-2015***

Symptoms

On Not Started activities, when modifying the value for the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost, the corresponding value of the Remaining Duration, Remaining Units, or Remaining Cost is not changing. The reverse is also true: when modifying the Remaining Duration or Remaining Units, the Original/Planned Duration, Budgeted/Planned Units, or Budgeted/Planned Cost are not updating.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a