ASCP New Material Plan Shows Previous Horizon & Some Of Week Buckets Drill Down To Days Is Disabled

(Doc ID 1591529.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.8 and later
Information in this document applies to any platform.
MSCBISUB.pls
Msc_Get_Bis_Values
PlanningUI

Symptoms

Using Advanced Supply Chain Planning / User Interface
On VCP 12.1.3.8 or 12.1.3.9:
When attempting to use the New Material Plan to view a given plan,
find that New Material Plan is showing dates from March 26, 2013
even though plan has been run several times and days the horizon start is not updated.

In the classic horizontal plan, the horizon start is correctly displayed.

When customer looked further out in the horizon,
the week buckets view of New Material Plan for four weeks do not have option to drill down to days bucket,
even though the plan has been run with days bucket for that time period.

EXPECTED BEHAVIOR
-----------------------------------

Expect
a) New Material Plan to match Classic Horizontal plan by showing Horizon
with start date as plan run date
and
b) Week buckets 8/26/2013 and beyond in the New Material Plan would allow
expansion into day buckets (matching the Classic Horizontal plan and plan options).

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms