Error: "The Timesheet Period You Are Attempting To Create Cannot Overlap With An Existing Timesheet Period" Even Though Period Does Not Overlap
(Doc ID 1596616.1)
Last updated on NOVEMBER 15, 2019
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 8.2.0.0 and laterInformation in this document applies to any platform.
Symptoms
Symptom 1:
Users are not able to create certain timesheet periods under Administer>Enterprise Data>Timesheet Periods. When attempting to add the new period, the following error is received even though the period does not overlap.
The timesheet period you are attempting to create cannot overlap with an existing timesheet period.
Symptom 2:
Users are not able to create certain financial periods and receive the following error:
The Financial Period You Are Attempting to Create Cannot Overlap with an Existing Financial Period.
Symptom 3:
In Team Member 8.4, when attempting to view the Timesheet tab, the following error occurs.
Alert: Current Timesheet Period does not exist
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
Fix 1: |
Fix 2: |
References |