Resource Assignments' Finish Dates Do Not Change When Changing Activity Finish Date (Doc ID 1600897.1)

Last updated on MARCH 09, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 6.2.1 and later
Information in this document applies to any platform.

Goal

When changing the Finish date of an activity, the Finish dates of resource assignments do not change (except for resources with Drive activity Dates turned on)

See steps below:

1. Open a project with Task Dependent activities that have multiple resources assigned (both driving and non driving)
2. Change the Finish Date of the Activity
3. Dates of resource assignments haven't changed (except resource with Drive Activity Dates)
4. Turn on Drive Activity Dates for all resource assignments
5. Change the Finish Date of the Activity
6. Dates of resource assignments haven't changed (except resource with Drive Activity Dates)
7. Turn off Drive Activity Dates for all resource assignments
8. Change the Finish Date of the Activity
9. Dates of resource assignments have changed

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms