Why Forecast Being Considered By ASCP Within Demand Time Fence (Doc ID 1604899.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

On : 12.1.3 version, Memory Based Planner

 Why forecast is being considered by ASCP even though the forecast is within the demand time fence ?
 The demand time fence for the item/org is set to 20 days yet a forecast is showing in supply/demand for 11/25/13.

 We need the forecast to be ignored within demand time fence.
 

Solution