Durations Being Divided By 8 After Converting P3 Project to P6 Format.

(Doc ID 1607008.1)

Last updated on JUNE 29, 2016

Applies to:

Primavera P6 Professional Project Management - Version 6.2 and later
Information in this document applies to any platform.

Symptoms

After using the P3 to P6 file converter, activity durations are being divided by 8, yet the dates display correctly.

Cause