REPORTDATE Table Is Not Backfilling Dates Based On Settings Change (Doc ID 1634364.1)

Last updated on MAY 04, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.2.0.0 and later
Information in this document applies to any platform.
The REPORTDATE table is storing data based on the settings in Administer > Application Settings > Services > Publication Period

The earliest DAYDATE value is the the "Start date" value.
The latest DAYDATE value is calculated based on the current system date plus the value set for "Finish date is current date plus".

Symptoms

When changing the start date in the Publication settings, the earliest DAYDATE is not changed to reflect the settings change.

Changes

 

Cause