Missing Relationships When Importing a Microsoft Project Schedule Into Primavera Risk Analysis. (Doc ID 1641065.1)

Last updated on JULY 26, 2017

Applies to:

Primavera Risk Analysis - Version 7.8 and later
Information in this document applies to any platform.

Symptoms

Missing links when importing Microsoft Project file into Primavera Risk Analysis.

Not all relationships for an activity / task are being imported when importing an MSP file into PRA.

Predecessors / Successors missing when importing a schedule into PRA.

What is the maximum number of relationships / links that can be assigned to a task / activity?

 

Cause