Finish Date of Milestone Incorrect When Importing P6 XML into Microsoft Project

(Doc ID 1645313.1)

Last updated on JULY 24, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.2.2.0 and later
Information in this document applies to any platform.

Symptoms

Finish milestone date incorrect after a P6 XML file is imported into MSP.

Using MSP 2010 to import P6 XML file.

Finish milestone has constraint applied that is different than the actual date of the milestone.

Cause