Symptoms

  We are trying to run SyncPDC to make the first Sync , but we are getting an error on the Load Work Action as shown :

[pindev@xyz bin]$ ./startSyncPDC
Creating PID file ..
Starting SyncPDC ...
PLEASE ENTER KEY PASSWORD TO DECRYPT THE PASSWORD(S) :
Clean up work item SYNC_EVENT...
Work item SYNC_EVENT started (item 1 of 8).
Processing EXTRACT work action...
Work action EXTRACT completed.
Processing ANALYZE work action...
Work action ANALYZE completed.
Processing TRANSFORM work action...
Work action TRANSFORM completed.
Processing LOAD work action...
Data migration Errors: One or more errors were encountered during data migration!
SyncPDC: there is an error during SyncPDC. Check SyncPDC log file for detail.
Removing /u01/pindev/brm_integration_pack/apps/syncpdc/syncpdc.pid

  

 

While running syncPDC, if this "skipBREMigration" parameter is set to false , then the following error is encountered

  


We tried to search for this BatchEvent in the source xml files , but couldnt find where it came from

How to fix or remove this issue so this eventAttribute dont break the sync ?

Note : If I change the value skipBREMigration in the config XML the utility works fine , however There are no customizations. What can we do to fix this error in the OOB so we can run the utility without the skipBREMigration parameter set to true ?

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.