PS: EBS: Mass Change Option For Work Order Dates Is Grayed Out (Doc ID 1673274.1)

Last updated on NOVEMBER 09, 2015

Applies to:

Oracle Production Scheduling - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : Production Scheduling (PS) 12.1.3 version, Everything in the User Interface plus Concurrent Mgr. Programs
PS build C673

ACTUAL BEHAVIOR
---------------
When trying to mass change for the work order dates 'Earliest Start Date' section, options 'Advance By' and 'Reduce By' are grayed out.

EXPECTED BEHAVIOR
-----------------------
These options should not be grayed out and activated

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Open the model in PS
2. Right Click on the WO folder
3. Change -> Check the Earliest Start Date section

Cause

Sign In with your My Oracle Support account