EBS: PS: Changing Resource Capacity In Work Order Operation (Doc ID 1677889.1)

Last updated on NOVEMBER 09, 2015

Applies to:

Oracle Production Scheduling - Version 11.5.10.2 and later
Information in this document applies to any platform.

Goal

Setup - You have setup the resource in the routing and assigned the number of units for the resource in the routing. This data is seen as expected on the discrete job and in PS.

Requirement is to change the number of assigned resource units in the work order operation within PS and repair solve.
 

Solution