OTHER ORGANIZATIONS' PROCESSING LEAD TIME IS USED ON PLANNED ORDER

(Doc ID 1917617.1)

Last updated on JANUARY 03, 2018

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
On EDD plan, Processing lead time in item attribute differently for the two organizations, Org1, Org2. But Org1 Processing lead time is used for Org2 planned order.

Item:ITEM_A
Org=Org1 ,Processing LT=60
Org=Org2 ,Processing LT=5

On Plan result, planned order is created for org:Org2 but it is scheduled with Processing LT 60, which is defined for Org1.

Item:ITEM_A (Buy Item)
Org=Org1
Planned Order
Sugg Due Date   :17-OCT-2014
Sugg Doc Date   :15-OCT-2014
Sugg Order Date :09-JUL-2014

Item:ITEM_A (Buy Item)
Org=Org2
Planned Order
Sugg Due date   :24-OCT-2014
Sugg Doc Date   :22-OCT-2014
Sugg Order Date :16-JUL-2014


EXPECTED BEHAVIOR
Processing Lead time defined for Org2 should be used for Org2 planned order.


STEPS
The issue can be reproduced at will with the following steps:

  1. Set Processing Lead time for a buy item.
    Org=Org1 ,Processing LT=60
    Org=Org2 ,Processing LT=5
  2. Run Data Collection and Plan.


BUSINESS IMPACT
Invalid Suggested Order date is set for Org2 planned order.

Changes

 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms