Symptoms

On : 12.1.3.8 version, Planning Engine

ACTUAL BEHAVIOR
---------------
There is a material supply for an item which is used earlier in the schedule. Additional supply is injected later which is enough to meet all requirements.

EXPECTED BEHAVIOR
-----------------------
Supply that actually comes late should be scheduled early since it can meet all requirements.