EBS: PS: PS Solver Crashes Due To Calendar Event (Doc ID 1918631.1)

Last updated on NOVEMBER 09, 2015

Applies to:

Oracle Production Scheduling - Version 12.1.3.8 and later
Information in this document applies to any platform.

Symptoms

On : Production Scheduling (PS) 12.1.3.8 version, Planning Engine
PS build 12.1.3.8 C633

ACTUAL BEHAVIOR
---------------
When the calendar event is changed from delay to down time, PS solve goes infeasible

EXPECTED BEHAVIOR
-----------------------
PS solve should complete successfully


Cause