EDD PLAN SETS DEMAND SUGG DUE DATE DAY BEFORE PLAN START DATE 23:59 (Doc ID 1919108.1)

Last updated on JUNE 28, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Memory Based Planner

ACTUAL BEHAVIOR
---------------

In EDD Plan, set a manual MDS or MDS loading Sales Order and perform ASCP. The demand sugg due date is being set to day before plan start date 23:59.


EXPECTED BEHAVIOR
-----------------------
In EDD Plan, when setting demand data such as manual MDS or MDS loading Sales Order and perform ASCP, sugg due date for the demand should be set to the desired date set on the mds form.


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Set a MDS (manual MDS or MDS loading Sales Order)
2. Perform data collection

Plan : Collection

 Org         Item                            Order Type           Sugg Due Date
 ----------------------------------------------------------------------
 TST:M1   Item_A00000000001  Sales order MDS    19-JUL-2013 00:00:00
 TST:M1   Item_A00000000001  Manual Demand     30-AUG-2013 00:00:00

3. Perform EDD plan (Plan Start Date : 2013/6/13)

 Org         Item                            Order Type           Sugg Due Date         
 -----------------------------------------------------------------------
 TST:M1   Item_A00000000001  Sales order MDS    12-JUN-2013 23:59:00
 TST:M1   Item_A00000000001  Manual Demand     12-JUN-2013 23:59:00

Sugg Due Date is set to 12-JUN-2013 23:59:00, which is the date before plan start date : 2013/6/13



Changes

 Applied the latest ASCP Engine patch

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms