Planned Orders Released From ASCP Suggested Dock/Due Date Not Matching With The Lines Created On PR
Last updated on JUNE 28, 2017
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.1.3.9 and laterInformation in this document applies to any platform.
Goal
When Planned Orders are released from ASCP, The PR created with need by dates is getting shuffled but not in an order or sequence of planned order lines released from ASCP.
Solution