EBS: PS: Bachable Resource Lot Multiple Not Matching With UOM Conversion From EBS

(Doc ID 1921835.1)

Last updated on JUNE 27, 2016

Applies to:

Oracle Production Scheduling - Version 12.2.3 and later
Information in this document applies to any platform.


On :  EBS - Production Scheduling (PS) 12.2.2 version, Data Collections from EBS products (717, 590 and 951) to Planning Data Store

When trying to setup a batchable resource in EBS, the lot multiple in the routing extracted into PS does not match the capacity of the batchable resource per spot.

According to the TOI, the lot multiple for a routing with a batchable resource is computed as the capacity of the machine per spot.