EBS: PS: Bachable Resource Lot Multiple Not Matching With UOM Conversion From EBS (Doc ID 1921835.1)

Last updated on JUNE 27, 2016

Applies to:

Oracle Production Scheduling - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

On :  EBS - Production Scheduling (PS) 12.2.2 version, Data Collections from EBS products (717, 590 and 951) to Planning Data Store

ACTUAL BEHAVIOR  
---------------
When trying to setup a batchable resource in EBS, the lot multiple in the routing extracted into PS does not match the capacity of the batchable resource per spot.

EXPECTED BEHAVIOR
-----------------------
According to the TOI, the lot multiple for a routing with a batchable resource is computed as the capacity of the machine per spot.

Cause

Sign In with your My Oracle Support account