Project Based Hard Pegging Enabled Plan With Decision Rule Enabled Fails With Signal 11 (Doc ID 1927029.1)

Last updated on AUGUST 19, 2019

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.9 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3.9 version, Memory Based Planner

When attempting to run Project based hard pegging enabled plan
with Profile Option MSO: Enable Decision Rule is Set to Yes,
the following error occurs.

ERROR
-----------------------
DSM om->createAbstEntities(), time taken = 1.93333
MSO_SCO_ASSIGNED_UNITS: 1
MSO_SCO_MAXIMIZE_POWO = 0
MSO_SCO_EXIST_SUPP_ABR_SUBSCOMP = 0
MSO_SCO_COST_ROLLUP_INCR_FACTOR = 1
MSO_SS_PLAN_LEVEL: 1
<MSO_TOP>/bin/MSONWL64.exe
Program was terminated by signal 11


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Advanced Supply Chain Planner Responsibility
2. Set profile Option MSO: Enable Decision Rule is Set to Yes
3. Launch Project based hard pegging enabled plan
 

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.