Symptoms

On : 12.1.3.9 version, Memory Based Planner

When attempting to run Project based hard pegging enabled plan
with Profile Option MSO: Enable Decision Rule is Set to Yes,
the following error occurs.

ERROR
-----------------------
DSM om->createAbstEntities(), time taken = 1.93333
MSO_SCO_ASSIGNED_UNITS: 1
MSO_SCO_MAXIMIZE_POWO = 0
MSO_SCO_EXIST_SUPP_ABR_SUBSCOMP = 0
MSO_SCO_COST_ROLLUP_INCR_FACTOR = 1
MSO_SS_PLAN_LEVEL: 1
/u01/vcpref/apps/apps_st/appl/mso/12.0.0/bin/MSONWL64.exe
Program was terminated by signal 11


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Advanced Supply Chain Planner Responsibility
2. Set profile Option MSO: Enable Decision Rule is Set to Yes
3. Launch Project based hard pegging enabled plan
 

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms