Planned Order Genereated In Period Where Resourec Calendar Is Off

(Doc ID 1927131.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.


On : 12.1.3 version, Memory Based Planner

Planned order generated in period when resource calendar is off.
The issue is still visible after patch 18607922

resource 66181-OPA
start date 13 Jul 2014
end date 20 Jul 2014
order type : planned order

no planned orders should be generated during resource unavailability

The issue can be reproduced at will with the following steps:
1. Apply patch 18607922
2. Run plan and verify results