 On : 12.1.3 version, Memory Based Planner

Users are running an Unconstrained ASCP plan and they see it creating Planned orders for supply earlier than needed . There are no order modifiers. For an example they see planned order qty = 1 due 14-NOV-2014 and it pegs to Forecast demand due 16-JAN-2015

Another example shows planned order qty = 2 pegged to qty = 1 Forecast Demand due 16-JAN-2015 and pegged qty = 1 Forecast demand due 23-JAN-2015