Issue in PS 12.1.3 C678
Application: PS Engine
----------------------------

ACTUAL BEHAVIOR
---------------
The Routing has multiple operation steps with same resources. While the PS offloads the capacity to an alternate resource, the PS doesn’t use same alternate resource across the routing even though the Profile option: MSC: PS Consistent Resource Assignment is enabled.

EXPECTED BEHAVIOR
-----------------------
Expecting PS to offload the alternate resource to the same resource in both the operations.



Cause