EBS: PS - PS Solve Results In Infeasible Schedule In A JIT Mode

(Doc ID 1934991.1)

Last updated on MARCH 30, 2017

Applies to:

Oracle Production Scheduling - Version and later
Information in this document applies to any platform.


Issue in PS C622
Application: PS Engine

When attempting to solve the model with a JIT model

Schedule infeasible

<<< Solve Failed !!! >>>

Schedule: GE-SlotPDS
Error: Insufficient Resource Capacity
  Resource "HST Eng Lb"
  Time Date Time: 2015/04/10 00:00:00
  Capacity Level: 1000
  NumConsumers Number: 25

The issue can be reproduced at will with the following steps:
1. Open the PS model
2. Solve the PS model