EBS: PS: Work Orders Appearing In PS Plan Even Though No WOs Are In ASCP Plan (Doc ID 1945609.1)

Last updated on NOVEMBER 09, 2015

Applies to:

Oracle Production Scheduling - Version 12.1.3.9 and later
Information in this document applies to any platform.

Goal

 On : EBS - Production Scheduling (PS) 12.1.3.9 version, Data Collections from EBS products (717, 590 and 951) to Planning Data Store

ACTUAL BEHAVIOR
-----------------
PS plan has an ASCP plan reference; the ASCP plan does not net WIP, so there are no work orders at all in the ASCP plan output. When the PS model is created, a work order that is in ODS appears in PS along with all planned orders from ASCP.

EXPECTED BEHAVIOR
-----------------------
PS should only have supplies and demands when referenced on an ASCP plan. No work orders should appear if they are not present in the ASCP plan

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms