P6 Adapter Response Error "RemainingEarlyFinishDate: Remaining Finish Cannot Be Earlier Than Remaining Start (Doc ID 1954296.1)

Last updated on JUNE 15, 2016

Applies to:

Primavera Gateway - Version 1.0 and later
Information in this document applies to any platform.

Symptoms

When attempting to import data from 3rd Party Provider (SAP) to Primavera P6 via the Primavera Gateway the following error occurs in the P6AdapterResponse:

RemainingEarlyFinishDate: Remaining Finish cannot be earlier than Remaining Start.
PlannedFinishDate: Planned Finish cannot be earlier than Planned Start.

 

Cause