EBS-PS : Work Orders Firmed At EBS Header Level Are Moved Outside Fixed Time Fence in PS (Doc ID 1960979.1)

Last updated on JUNE 02, 2017

Applies to:

Oracle Production Scheduling - Version 12.1.3.9 and later
Information in this document applies to any platform.

Symptoms

When a work order is firmed only at the header level in EBS and snapshot into PS, the corresponding work order is firmed only at the header level  not at operation level in PS. When this firm work order falls inside the fixed time fence, PS pushes these work orders/operations outside the fixed time fence instead of planning inside the time fence

Cause