Positive Cost Value In Actual This Period Cost Even Though Actual This Period Units Set To Zero (Doc ID 1962050.1)

Last updated on JUNE 30, 2016

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 7.0 and later
Information in this document applies to any platform.

Symptoms

The Actual This Period Cost field is displaying a positive cost value when expecting it to display a zero value. The corresponding Actual This Period Units field is set with zero units and the Activity to which resource is assigned has been progressed and period closed out.

Changes

The Resource being used in the Resource Assignment has varying resource rates.

The Activity to which resource is assigned has been progressed (actuals applied).

Store Period Performance has been executed to store period performance for earlier periods of the Resource Assignment.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms