Sometimes ASCP Ignores Post Process Leadtime. Why Due Date = Dock Date = Ship Date? Weekly Bucket Compression (Doc ID 1964776.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.9 and later
Information in this document applies to any platform.

Goal

Sometimes the suggested due date in BA1 is not taking into calculation POST processing LT.

A. In this test case due date at Feb-7(Saturday) it's weekend, holiday. We have 5 day org calendar in use.
Now dock date is 6-Feb + 1 day PPLT shall be 9-Feb, because 7, 8 Feb are day off. In this case why 7-feb due date are not calculated to be on working day?

B. There is planned order 972199078 ... it has sugg ship date = sug dock date = 20-Feb-2015, but sugg due date = 27-Feb-2015.

? So order 972199078 also are in weekly bucket but dates are calculated differently.

Can you answer questions:
1) Does it mean that in weekly buckets plan ignores calendar and all dates are calculated on Friday?
2) Why planned order 972199078 sugg due date is 1 week from sugg ship date, but for 972199077 sug due date = sugg ship date?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms